Indian Ambassador Sudhakar Dalela (left) during a courtesy meeting with Minister for Energy, Irrigation and Water Resources Biraj Bhakta Shrestha on Tuesday.
KATHMANDU: India has permitted the supply of 350 megawatts of electricity to Nepal during the winter season.
According to the Ministry of Energy, Irrigation and Water Resources, the southern neighbor has also approved an additional 56 MW of power exports from Nepal during the wet season.
Indian Ambassador to Nepal Sudhakar Dalela informed Minister for Energy, Irrigation and Water Resources Biraj Bhakta Shrestha about the decisions during a meeting at the energy ministry on Tuesday.
Sanjiv Maharjan, chief personal secretary to Minister Shrestha, said Ambassador Dalela said India had decided to provide the necessary electricity to Nepal to help manage winter demand.
The devastating floods in the Bhotekoshi River in August knocked 431 MW of electricity generation capacity out of the national grid. Subsequent floods in the Kaligandaki and Budhigandaki rivers also damaged power infrastructure.
Minister Shrestha had also discussed the smooth supply of electricity with visiting Indian Foreign Secretary Vikram Misri during a courtesy meeting at the ministry a few days ago. Before that, ministry officials had held discussions on the issue with the Indian energy secretary during his visit to Nepal.
Dirghayu Kumar Shrestha, managing director of the Nepal Electricity Authority (NEA), said the utility had received permission to import electricity from the Indian market from November 17, 2026, to July 30, 2027.
“Following several rounds of discussions involving the minister and his team, the ministry and the NEA, India has agreed to supply 350 megawatts of electricity during peak hours in the dry season. This will help meet demand during winter and make supply management easier,” he added.
India’s Central Electricity Authority has authorized the NEA to import electricity at competitive rates from the Day-Ahead Market and Real-Time Market of the Indian Energy Exchange (IEX) for up to 17 hours a day. Nepal can import electricity at any time except between 5 am and 8 am and between 5 pm and 9 pm.
NEA can import 300 MW through the 132 kV Kataiya-Kushaha, Raxaul-Parwanipur and Ramnagar-Surajpura transmission lines, and another 50 MW through the 132 kV New Nautanwa-Mainahiya transmission line.

Himal Press