KATHMANDU: The Public Accounts Committee of the House of Representatives has directed the Ministry of Energy, Water Resources and Irrigation to submit all documents related to the cancellation of the tender process for the Sunkoshi-Marin Multipurpose Diversion Project within seven days.
Speaking at a committee meeting Tuesday, Rastriya Prajatantra Party (RPP) lawmaker Khusbu Oli questioned what led the government to cancel the new tender. She also asked why the project was facing delays, whether there was political or administrative interference, and whether Dinesh Rajauria, director general of the Department of Water Resources and Irrigation, had visited the Office of the Prime Minister regarding the contract cancellation.
“Did you visit the Office of the Prime Minister or not? I want an answer,” she said.
Rajauria, who was present in the meeting, confirmed he visited the office that day. “But I did not feel any interference,” he said, insisting that the tender was canceled in accordance with existing laws.
Then-Energy Minister Kulman Ghising terminated the Rs 14.07 billion contract with Patel-Raman JV in October last year after physical progress fell significantly behind schedule. The new tender process, launched in June for civil, hydromechanical, dam and powerhouse works, was canceled on October 30, just before financial proposals were opened, reportedly under pressure from the Office of the Prime Minister.
Manish Jha of the ruling Rastriya Swatantra Party (RSP) sought a clear explanation for suspending work on the Sunkoshi-Marin Diversion Project.
“If this national pride project is canceled, people in Madhesh will have no option but to take to the streets,” he said.
The project aims to divert water from the Sunkoshi River into the Marin River to irrigate roughly 180,000 bighas of farmland across parts of Bara, Rautahat, Sarlahi, Mahottari and Dhanusha districts.
Jha demanded clear answers on three issues: why the project was halted, what circumstances led to the contract cancellation and how the government plans to move the project forward.